Borrow-Pit Method
Borrow-Pit Method
- Not suitable for linear features, very useful for construction sites.
- The site is divided into equal squares of sides 20,50, or a 100 ft. Elevations are then measured at the corners of the grid, which are given names that correspond to the corner coordinate in the grid, ex: 3-D, 4-A,..
- V = (sum (hijn)) A yd3
- 4*27
- The idea is to multiply each height by the number of complete squares it is common.