Class 8 RCW

RCW 4.24.360
Construction contract provision waiving, releasing, etc.,
rights of contractor, etc., to damages or adjustment
for unreasonable delay caused by contractee, etc.—
Declared void and unenforceable—Exceptions.

Any clause in a construction contract, as defined in RCW 4.24.370, which purports to waive, release, or extinguish the rights of a contractor, subcontractor, or supplier to damages or an equitable adjustment arising out of unreasonable delay in performance which delay is caused by the acts or omissions of the contractee or persons acting for the contractee is against public policy and is void and unenforceable.

This section shall not be construed to void any provision in a construction contract, as defined in RCW 4.24.370, which (1) requires notice of delays, (2) provides for arbitration or other procedure for settlement, or (3) provides for reasonable liquidated damages.

[1979 ex.s. c 264 § 1.] Class Absher Hensel Johnson II Rowland Glossary

RCW 4.24.370
Construction contract provision waiving, releasing, etc.,
rights of contractor, etc., to damages or adjustment
for unreasonable delay caused by contractee, etc.—
“Construction contract” defined.

“Construction contract” for purposes of RCW 4.24.360 means any contract or agreement for the construction, alteration, repair, addition to, subtraction from, improvement to, or maintenance of, any building, highway, road, railroad, excavation, or other structure, project, development, or improvement attached to real estate, including moving and demolition in connection therewith. [1979 ex.s. c 264 § 2.]

RCW 4.24.380
Construction contract provision waiving, releasing, etc.,
rights of contractor, etc., to damages or adjustment
for unreasonable delay caused by contractee, etc.—
Prospective application of RCW 4.24.360.

The provisions of RCW 4.24.360 shall apply to contracts or agreements entered into after September 1, 1979. [1979 ex.s. c 264 § 3.]