PROJECT MANAGEMENT DATA COMPILATION

The goal of compiling the project management data is to provide information on what we did and how long it took. This will help future FE 450 students as they plan for their projects, as well as providing documentation for the work you did. Compiling this data will ideally be a quarter-long process, with minimal work needed at the end of the quarter. This is dependent upon the effectiveness of the project management set-up. Comparisons can be made between the end results, and the predictions made prior to the start of the project. This will be a good measure of our ability to accurately predict and describe the process of the capstone project.

Back to Outline

Office: Mar. 25 - Apr. 13 Field: Apr. 16 - May 11
Office: May 14 - June 7

Overhead (meetings)

Field Work

Final Setting Design
Preliminary Planning   Final Road Design
First Day at Pack Forest   Final Alt. Harvest Sys. Analysis
Office Setup   Final Timber Modeling

Project Management Start-up

  Cost Analysis
Data Collection   Report
Basemaps   Final Maps
Production Equations   Presentation
Watershed Analysis   Presentation to DNR
Preliminary Timber Modeling   Project Mgmt Data Compilation

Preliminary Setting Design

 

Report Due

Prelim. Alt. Harvest Sys. Analysis    
Preliminary Road Design    

Preliminary Report Work

   
Field Preparation    
Field Maps